Davern Road Bridge Update

Peru – Oct. 10, 2019 The concrete beams have been installed and construction is rapidly proceeding on the new Davern Rd. Bridge.
On July 5th Clinton County awarded the contract to Luck Brothers Inc. of Plattsburgh who submitted a bid of $885,102.66. Luck Brothers has until December 6th to complete the project. Now it looks like it will open in early to mid-November.
Today dump trucks are dumping gravel adjacent to the bridge. The bridge deck is several feet higher than the existing road.
Posted: October 10th, 2019 under Highway Dept. News, Peru News.